Civil Engineering MCQAE Level Civil Engineering

The variance of a PERT activity duration is:

Construction ManagementConstruction Materials, Practices, Planning and ManagementHARD

Choose the correct answer

A

(a+4m+b)/6

B

(m-a)/(b-m)

C

((b-a)/6)^2

D

(b+a)^2/36

Correct Answer

C. ((b-a)/6)^2

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT activity standard deviation is (b - a)/6, so variance is [(b - a)/6]^2.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account