The Standard Penetration Test (SPT) N value is corrected for overburden pressure using the relation (Peck, 1974):
Choose the correct answer
N_c = N (no correction needed)
N_c = 0.77 log(2000/sigma_v) x N where sigma_v is effective overburden (kPa), applicable for sigma_v > 25 kPa
N_c = N x depth
N_c = N / 2
Correct Answer
B. N_c = 0.77 log(2000/sigma_v) x N where sigma_v is effective overburden (kPa), applicable for sigma_v > 25 kPa
Why is this the answer?
SPT N correction for overburden: Peck correction: N_c = 0.77 log(2000/sigma_v) x N for sigma_v > 25 kPa (no correction for sigma_v = 1 ton/ft2 = 100 kPa). Also water table correction: if water table is within B above footing: N_corrected = 0.5 N + 15 (Terzaghi). Corrected N used for bearing capacity and settlement.
Related Foundation Engineering MCQs
More solved Foundation Engineering questions for AE/JE Civil Engineering exams.
- A soil sample weighs 30 kN and occupies 1.0 m³. Bulk unit weight is
- A soil has water weight 10 N and dry solid weight 100 N. Water content is
- If water volume is 0.2 m³ and void volume is 0.5 m³, degree of saturation is
- For a soil mass, volume of voids is 0.5 m³ and total volume is 1.0 m³. Porosity is
- Using Darcy law, k=0.0001 m/s, hydraulic gradient=0.5 and area=2.0 m². Discharge is
- A soil sample has volume of voids 0.6 m³ and volume of solids 1.0 m³. Void ratio is