The primary advantage of a bar chart (Gantt chart) over a CPM network for site supervisors is:

Construction ManagementBar ChartMEDIUM

Choose the correct answer

A

It explicitly shows the critical path and total floats

B

It allows easy resource leveling across activities

C

It is simple to understand, prepare and update on site

D

It accounts for probabilistic activity durations

Correct Answer

C. It is simple to understand, prepare and update on site

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Bar charts are intuitive — each activity is a horizontal bar proportional to its duration. Site supervisors without planning training can read them easily. Their weakness: no dependency links between activities are shown, making impact analysis difficult — hence networks are used for planning while bar charts are used for monitoring.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account