The latest start of an activity is always
Choose the correct answer
equal to the latest event time of the preceding node
less than the latest event time of the preceding node
greater than or equal to the latest event time of the preceding node
independent of the latest event time of the preceding node
Correct Answer
C. greater than or equal to the latest event time of the preceding node
Why is this the answer?
For an activity i-j, the latest start time is LST = TL(j) - duration. The latest event time of the preceding node, TL(i), is the minimum of the latest start times of activities leaving that node. Hence an activity's LST is always greater than or equal to TL(i), with equality for at least one controlling outgoing activity.
Related Strength of Materials MCQs
More solved Strength of Materials questions for AE/JE Civil Engineering exams.
- In a 'statically indeterminate' structure, 'compatibility' equations ensure:
- The 'section classification' of steel sections in IS 800...
- The 'virtual work principle' states that for a system in equilibrium, if it undergoes a...
- In the 'Muller-Breslau principle', the influence line for a function (reaction, shear,...
- The 'direct stiffness' global matrix after assembly is generally:
- The 'approximate analysis' of building frames under lateral loads (portal frame method)...
Practice more Civil Engineering questions
This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.