Slack time in PERT analysis for critical activities is equal to:

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

zero

B

constant

C

negative

D

positive

Correct Answer

A. zero

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Critical path activities have zero slack/float