Civil Engineering MCQJE Level Civil Engineering

'Segmental bridge construction' using 'balanced cantilever' method means:

RCCRCCHARD

Choose the correct answer

A

Building from both abutments simultaneously without piers

B

Segments added symmetrically from each pier as paired cantilevers — no mid-span falsework; prestressed progressively

C

All segments cast at the same time using full formwork

D

Lifting pre-cast deck panels by cranes from the top

Correct Answer

B. Segments added symmetrically from each pier as paired cantilevers — no mid-span falsework; prestressed progressively

Why is this the answer?

Balanced cantilever: segments (2–5 m long precast or cast-in-place) built symmetrically in pairs from each pier outward (one segment each side alternately) → balanced overhanging cantilevers grow from pier without falsework touching ground below. Used for: navigable rivers, deep gorges, highways. Pre-stressing: cantilever tendons on top; after closure (midspan): additional bottom tendons. Typical span: 70–200 m. Famous examples: Bandra-Worli Sealink, metro viaducts.

Related RCC MCQs

More solved RCC questions for AE/JE Civil Engineering exams.

View all RCC MCQs →

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account