Security deposit in a works contract is primarily meant to safeguard:

Construction ManagementEstimating, Costing and Construction ManagementHARD

Choose the correct answer

A

Contractor's advertising cost

B

Daily labour attendance

C

Due performance of contract obligations

D

Cement fineness measurement

Correct Answer

C. Due performance of contract obligations

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Security deposit is retained as protection against non-performance or defects.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account