'Pre-stressed concrete' is preferred over ordinary RC when:

RCCRCCMEDIUM

Choose the correct answer

A

Only for short spans under heavy point loads

B

Long spans, crack-free requirements (liquid retaining), fatigue loading — high quality materials and skills required

C

Always replacing RC for all applications

D

When columns are taller than 3 m

Correct Answer

B. Long spans, crack-free requirements (liquid retaining), fatigue loading — high quality materials and skills required

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PSC preferred: (1) Long spans (> 10–15 m for beams, > 20 m for bridges) — less deflection, smaller cross-section; (2) When cracks must be absolutely avoided (water-retaining, nuclear structures); (3) Under fatigue loading — full section works in compression; (4) Reduces steel and concrete consumption by 25–50%. Disadvantage: higher material cost, skilled labour, specialised equipment.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account