Pick up the item of work not included in the plinth area estimate.
Strength of MaterialsEstimation & CostingMEDIUM
Choose the correct answer
A
Wall thickness
B
Verandah area
C
W.C. area
D
Courtyard area
Correct Answer
D. Courtyard area
Why is this the answer?
Plinth area covers the built-up area (including wall thickness and covered verandah); open courtyard area is excluded.
Related Strength of Materials MCQs
More solved Strength of Materials questions for AE/JE Civil Engineering exams.
- In a 'statically indeterminate' structure, 'compatibility' equations ensure:
- The 'section classification' of steel sections in IS 800...
- The 'virtual work principle' states that for a system in equilibrium, if it undergoes a...
- In the 'Muller-Breslau principle', the influence line for a function (reaction, shear,...
- The 'direct stiffness' global matrix after assembly is generally:
- The 'approximate analysis' of building frames under lateral loads (portal frame method)...
Practice more Civil Engineering questions
This MCQ belongs to WBPSC JE (Civil) Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.