Percentage rate tender is quoted as percentage above or below:
Construction ManagementEstimating, Costing and Construction ManagementMEDIUM
Choose the correct answer
A
Market rent only
B
Schedule of rates
C
Salvage value
D
Labour attendance
Correct Answer
B. Schedule of rates
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Contractor quotes a percentage relative to departmental rates.