Civil Engineering MCQJE Level Civil Engineering
One-way slab action occurs when longer span to shorter span ratio is:
RCCConcrete Technology, RCC and Steel DesignEASY
Choose the correct answer
A
Exactly 1.5 always
B
Equal to 1
C
Greater than 2
D
Less than 1
Correct Answer
C. Greater than 2
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Load is mainly carried in the shorter direction when Ly/Lx > 2.