One-way slab action occurs when longer span to shorter span ratio is:

RCCConcrete Technology, RCC and Steel DesignEASY

Choose the correct answer

A

Exactly 1.5 always

B

Equal to 1

C

Greater than 2

D

Less than 1

Correct Answer

C. Greater than 2

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Load is mainly carried in the shorter direction when Ly/Lx > 2.