Normal time=15 days, crash time=8 days, normal cost=Rs.10000, crash cost=Rs.16000. Cost slope is

Construction ManagementOriginal practiceMEDIUM

Choose the correct answer

A

Rs. 1714/day

B

Rs. 6000/day

C

Rs. 857/day

D

Rs. 429/day

Correct Answer

C. Rs. 857/day

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Cost slope=(crash cost-normal cost)/(normal time-crash time)=Rs. 857/day.