Negative slack occurs

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

when the latest allowable time is greater than the earliest expected time

B

when events stick to their schedule

C

when there is a deficiency of resources

D

None of the above

Correct Answer

D. None of the above

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Negative slack occurs when required latest time is earlier than earliest expected time; none of visible options exactly.