Lump sum contract is most suitable when:
Construction ManagementEstimating, Costing and Construction ManagementMEDIUM
Choose the correct answer
A
Work cannot be described
B
Scope and drawings are clearly defined
C
Quantities are highly uncertain
D
Design is changing daily
Correct Answer
B. Scope and drawings are clearly defined
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
A fixed total price is practical when work is fully defined.