Civil Engineering MCQJE Level Civil Engineering

Liquidated damages are imposed when the contractor:

Construction ManagementEstimating, Costing and Construction ManagementHARD

Choose the correct answer

A

Finishes work before schedule

B

Fails to complete within stipulated time

C

Uses a higher grade of concrete

D

Provides extra samples

Correct Answer

B. Fails to complete within stipulated time

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

LD is a pre-agreed compensation for delay.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap