In PERT, if the expected project duration Te = 20 weeks and standard deviation σ = 2 weeks, the probability of completing the project within 24 weeks (Z value for 2σ is 0.9772) is approximately:

Construction ManagementPERT ProbabilityMEDIUM

Choose the correct answer

A

50%

B

84.1%

C

97.7%

D

99.9%

Correct Answer

C. 97.7%

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Z = (T_s − Te)/σ = (24 − 20)/2 = 2.0. From normal distribution tables, P(Z ≤ 2.0) = 0.9772 ≈ 97.7%. This means a 97.7% chance of finishing by week 24 — schedule has generous buffer.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account