In PERT, if the expected project duration Te = 20 weeks and standard deviation σ = 2 weeks, the probability of completing the project within 24 weeks (Z value for 2σ is 0.9772) is approximately:
Construction ManagementPERT ProbabilityMEDIUM
Choose the correct answer
A
50%
B
84.1%
C
97.7%
D
99.9%
Correct Answer
C. 97.7%
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Z = (T_s − Te)/σ = (24 − 20)/2 = 2.0. From normal distribution tables, P(Z ≤ 2.0) = 0.9772 ≈ 97.7%. This means a 97.7% chance of finishing by week 24 — schedule has generous buffer.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.