In CPM scheduling, the project duration is governed by the path having:
Construction ManagementEstimating, Costing and Construction ManagementHARD
Choose the correct answer
A
Least material cost only
B
Smallest activity code
C
Maximum drawing number
D
Largest total duration
Correct Answer
D. Largest total duration
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
The critical path is the longest-duration path and fixes completion time.