Civil Engineering MCQJE Level Civil Engineering
In CPM, crashing is normally considered for an activity when reducing its duration is worth the added direct cost and the activity is:
Construction ManagementProject CrashingMEDIUM
Choose the correct answer
A
On the critical path or can affect it
B
Completely outside the network
C
Already having infinite free float
D
A material test with no duration
Correct Answer
A. On the critical path or can affect it
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Crashing shortens project duration only when applied to critical or near-critical activities.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.