In CPM, crashing is normally considered for an activity when reducing its duration is worth the added direct cost and the activity is:

Construction ManagementProject CrashingMEDIUM

Choose the correct answer

A

On the critical path or can affect it

B

Completely outside the network

C

Already having infinite free float

D

A material test with no duration

Correct Answer

A. On the critical path or can affect it

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Crashing shortens project duration only when applied to critical or near-critical activities.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account