In a Precedence Diagram Method (PDM) network, a 'Start-to-Start (SS) with lag of 3 days' relationship between activities A and B means:

Construction ManagementPrecedence DiagramHARD

Choose the correct answer

A

B can start only after A is fully complete

B

B can start 3 days after A has started — partial overlap is allowed

C

A must finish 3 days before B can finish

D

A and B must start simultaneously with no lag between them

Correct Answer

B. B can start 3 days after A has started — partial overlap is allowed

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PDM has four dependency types: FS (Finish-to-Start), SS (Start-to-Start), FF (Finish-to-Finish), SF (Start-to-Finish). SS+3 means B's start is constrained to be ≥ A's start + 3 days. This allows overlapping (fast-tracking) while ensuring B doesn't begin until A is 3 days into execution — critical for concurrent engineering and construction acceleration.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account