In a mock-test problem built around repetitive construction activities, which answer is most appropriate? Avoid the common trap that it is used only for truss analysis.
Construction ManagementLine of BalanceEASY
Choose the correct answer
A
it is useful for projects with repeated units like floors or roads
B
it replaces all cost control
C
it cannot show crew progress
D
it is used only for truss analysis
Correct Answer
A. it is useful for projects with repeated units like floors or roads
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
LOB helps plan repetitive work flow. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.