Civil Engineering MCQJE Level Civil Engineering
In a mock-test problem built around probabilistic activity duration, which answer is most appropriate? Avoid the common trap that pessimistic time is ignored.
Construction ManagementPERTMEDIUM
Choose the correct answer
A
PERT uses only one fixed duration
B
expected time is commonly based on optimistic, most likely and pessimistic estimates
C
pessimistic time is ignored
D
PERT is a soil test
Correct Answer
B. expected time is commonly based on optimistic, most likely and pessimistic estimates
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
PERT handles uncertainty in activity durations. Correct option: B.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap