In a mock-test problem built around deterministic project scheduling, which answer is most appropriate? Avoid the common trap that cPM ignores activity durations.

Construction ManagementCPMEASY

Choose the correct answer

A

CPM ignores activity durations

B

critical path is always the shortest path

C

critical path has zero total float in the basic network

D

float is measured only in rupees

Correct Answer

C. critical path has zero total float in the basic network

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

CPM identifies activities controlling project duration. Correct option: C.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account