In a mock-test problem built around deterministic project scheduling, which answer is most appropriate? Avoid the common trap that cPM ignores activity durations.
Construction ManagementCPMEASY
Choose the correct answer
A
CPM ignores activity durations
B
critical path is always the shortest path
C
critical path has zero total float in the basic network
D
float is measured only in rupees
Correct Answer
C. critical path has zero total float in the basic network
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
CPM identifies activities controlling project duration. Correct option: C.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap