Civil Engineering MCQJE Level Civil Engineering
In a mock-test problem built around delay without affecting successor early start, which answer is most appropriate? Avoid the common trap that free float is concrete slump.
Construction ManagementFree FloatHARD
Choose the correct answer
A
free float ignores successors
B
free float is always larger than project duration
C
free float cannot exceed total float
D
free float is concrete slump
Correct Answer
C. free float cannot exceed total float
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Free float concerns immediate successor timing. Correct option: C.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.