In a mock-test problem built around cost and schedule performance, which answer is most appropriate? Avoid the common trap that actual cost is never recorded.
Construction ManagementEarned ValueMEDIUM
Choose the correct answer
A
earned value compares planned value, earned value and actual cost
B
actual cost is never recorded
C
schedule variance is always zero
D
earned value uses only rainfall
Correct Answer
A. earned value compares planned value, earned value and actual cost
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
EVM integrates scope, cost and schedule progress. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.