In a mock-test problem built around cost and schedule performance, which answer is most appropriate? Avoid the common trap that actual cost is never recorded.

Construction ManagementEarned ValueMEDIUM

Choose the correct answer

A

earned value compares planned value, earned value and actual cost

B

actual cost is never recorded

C

schedule variance is always zero

D

earned value uses only rainfall

Correct Answer

A. earned value compares planned value, earned value and actual cost

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

EVM integrates scope, cost and schedule progress. Correct option: A.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account