In a CPM network, the TOTAL float of an activity is the maximum time it can be delayed without delaying the project. An activity with ZERO total float is called a:

Construction ManagementProject Network CPM FloatMEDIUM

Choose the correct answer

A

Sub-critical activity

B

Critical activity (on the critical path)

C

Dummy activity

D

Free activity

Correct Answer

B. Critical activity (on the critical path)

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Critical path = longest path through network; all activities on it have TF = 0. Total float TF = LST - EST = LFT - EFT = LFT - EST - D. Free float FF = EST(next) - EFT. Independent float = EST(next) - LFT(preceding) - D. Reducing the duration of a critical activity reduces project duration by the same amount.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account