In a CPM network, activities A(6 days), B(4 days) and C(3 days) exist where B and C both start after A and the project ends when both B and C finish. The project duration is:

Construction ManagementProject NetworkMEDIUM

Choose the correct answer

A

13 days

B

10 days

C

7 days

D

9 days

Correct Answer

B. 10 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Critical path = A → B = 6 + 4 = 10 days. Path A → C = 6 + 3 = 9 days. B is critical; C has 1 day total float. Activities in parallel: only the longest path determines project duration.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account