Civil Engineering MCQJE Level Civil Engineering
If contractor's quoted rate is 12 percent above SOR rate Rs 500, the quoted rate is:
Construction ManagementEstimating, Costing and Construction ManagementHARD
Choose the correct answer
A
Rs 512
B
Rs 540
C
Rs 620
D
Rs 560
Correct Answer
D. Rs 560
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Quoted rate = 500 x 1.12 = Rs 560.