If an activity has optimistic, most-likely and pessimistic times of 2, 3 and 7 respectively, the expected time and variance are
Strength of MaterialsStrength of MaterialsMEDIUM
Choose the correct answer
A
3.5 and 5/6
B
5 and 25/36
C
5 and 5/6
D
3.5 and 25/36
Correct Answer
D. 3.5 and 25/36
Why is this the answer?
PERT expected time =3.5 and variance=(5/6)^2=25/36.
Related Strength of Materials MCQs
More solved Strength of Materials questions for AE/JE Civil Engineering exams.
- In a 'statically indeterminate' structure, 'compatibility' equations ensure:
- The 'section classification' of steel sections in IS 800...
- The 'virtual work principle' states that for a system in equilibrium, if it undergoes a...
- In the 'Muller-Breslau principle', the influence line for a function (reaction, shear,...
- The 'direct stiffness' global matrix after assembly is generally:
- The 'approximate analysis' of building frames under lateral loads (portal frame method)...
Practice more Civil Engineering questions
This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.