Civil Engineering MCQAE Level Civil Engineering
If an activity has optimistic, most-likely and pessimistic times of 2, 3 and 7 respectively, the expected time and variance are
Strength of MaterialsStrength of MaterialsMEDIUM
Choose the correct answer
A
3.5 and 5/6
B
5 and 25/36
C
5 and 5/6
D
3.5 and 25/36
Correct Answer
D. 3.5 and 25/36
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
PERT expected time =3.5 and variance=(5/6)^2=25/36.