Civil Engineering MCQAE Level Civil Engineering

If an activity has optimistic, most-likely and pessimistic times of 2, 3 and 7 respectively, the expected time and variance are

Strength of MaterialsStrength of MaterialsMEDIUM

Choose the correct answer

A

3.5 and 5/6

B

5 and 25/36

C

5 and 5/6

D

3.5 and 25/36

Correct Answer

D. 3.5 and 25/36

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT expected time =3.5 and variance=(5/6)^2=25/36.