Civil Engineering MCQAE Level Civil Engineering
If activity quantity is 200 units and labour/equipment cost is Rs.100 per unit, direct cost is
Construction ManagementOriginal practiceMEDIUM
Choose the correct answer
A
Rs. 10000
B
Rs. 20000
C
Rs. 300
D
Rs. 40000
Correct Answer
B. Rs. 20000
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Direct cost=quantity×unit cost=200×100=Rs.20000.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.