If activity quantity is 200 units and labour/equipment cost is Rs.100 per unit, direct cost is

Construction ManagementOriginal practiceMEDIUM

Choose the correct answer

A

Rs. 10000

B

Rs. 20000

C

Rs. 300

D

Rs. 40000

Correct Answer

B. Rs. 20000

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Direct cost=quantity×unit cost=200×100=Rs.20000.