If a contractor quotes 6 percent above Rs 850 per unit, the quoted rate is:

Construction ManagementEstimating, Costing and Construction ManagementHARD

Choose the correct answer

A

Rs 901 per unit

B

Rs 956 per unit

C

Rs 799 per unit

D

Rs 856 per unit

Correct Answer

A. Rs 901 per unit

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Rate = 850 x 1.06 = Rs 901. This gives the answer: Rs 901 per unit.