Gantt chart is drawn for:

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

time versus activity

B

time versus progress

C

resources versus progress

D

progress versus time

Correct Answer

A. time versus activity

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

A Gantt chart shows activities along a time scale