Free float of an activity is the time by which it can be delayed without affecting:
Construction ManagementEstimating, Costing and Construction ManagementHARD
Choose the correct answer
A
Salvage value of plant
B
Initial administrative approval
C
Earliest start of the succeeding activity
D
Theoretical cement volume
Correct Answer
C. Earliest start of the succeeding activity
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Free float measures delay possible without disturbing immediate successors.