Free float of an activity is the time by which it can be delayed without affecting:

Construction ManagementEstimating, Costing and Construction ManagementHARD

Choose the correct answer

A

Salvage value of plant

B

Initial administrative approval

C

Earliest start of the succeeding activity

D

Theoretical cement volume

Correct Answer

C. Earliest start of the succeeding activity

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Free float measures delay possible without disturbing immediate successors.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account