Civil Engineering MCQAE Level Civil Engineering
Free float is the delay possible without affecting:
Construction ManagementConstruction Materials, Practices, Planning and ManagementHARD
Choose the correct answer
A
latest finish of last activity
B
project cost only
C
resource histogram only
D
earliest start of succeeding activity
Correct Answer
D. earliest start of succeeding activity
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Free float is the time an activity can be delayed without delaying the early start of any immediate successor.