Civil Engineering MCQAE Level Civil Engineering

For three-dimensional movement of a weight at a construction site, which machinery is most suitable?

Construction ManagementConstruction ManagementMEDIUM

Choose the correct answer

A

Chain hoist

B

Winch

C

Crane

D

Jack

Correct Answer

C. Crane

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

A crane provides lift, horizontal travel and slewing — full 3-D movement.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account