For field interpretation of Total Float, the issue is allowable delay of an activity. What should be selected? Avoid the common trap that it is independent of network logic.
Construction ManagementTotal FloatMEDIUM
Choose the correct answer
A
it equals direct cost
B
it is the time an activity can be delayed without delaying project completion
C
it is independent of network logic
D
it is always negative
Correct Answer
B. it is the time an activity can be delayed without delaying project completion
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Total float measures scheduling flexibility. Correct option: B.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.