For field interpretation of Tendering, the issue is selection of contractor. What should be selected? Avoid the common trap that tendering is only material testing.

Construction ManagementTenderingMEDIUM

Choose the correct answer

A

lowest number is accepted even if non-responsive

B

qualification has no relevance

C

bid evaluation considers responsiveness, price and qualification criteria

D

tendering is only material testing

Correct Answer

C. bid evaluation considers responsiveness, price and qualification criteria

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Tender evaluation checks compliance and capability. Correct option: C.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account