Civil Engineering MCQJE Level Civil Engineering
For field interpretation of Resource Levelling, the issue is adjusting schedule to smooth resource demand. What should be selected? Avoid the common trap that resource demand is ignored.
Construction ManagementResource LevellingMEDIUM
Choose the correct answer
A
resource demand is ignored
B
levelling means changing concrete level only
C
non-critical activities may be shifted within float
D
critical activities are always deleted
Correct Answer
C. non-critical activities may be shifted within float
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Resource levelling balances resource usage against schedule. Correct option: C.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.