PERT uses only one fixed duration
B
pessimistic time is ignored
C
expected time is commonly based on optimistic, most likely and pessimistic estimates
D
PERT is a soil test
Correct Answer
C. expected time is commonly based on optimistic, most likely and pessimistic estimates
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
PERT handles uncertainty in activity durations. Correct option: C.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.