For field interpretation of PERT, the issue is probabilistic activity duration. What should be selected? Avoid the common trap that pERT is a soil test.

Construction ManagementPERTMEDIUM

Choose the correct answer

A

PERT uses only one fixed duration

B

pessimistic time is ignored

C

expected time is commonly based on optimistic, most likely and pessimistic estimates

D

PERT is a soil test

Correct Answer

C. expected time is commonly based on optimistic, most likely and pessimistic estimates

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT handles uncertainty in activity durations. Correct option: C.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account