Civil Engineering MCQJE Level Civil Engineering

For field interpretation of Line of Balance, the issue is repetitive construction activities. What should be selected? Avoid the common trap that it replaces all cost control.

Construction ManagementLine of BalanceEASY

Choose the correct answer

A

it is used only for truss analysis

B

it is useful for projects with repeated units like floors or roads

C

it cannot show crew progress

D

it replaces all cost control

Correct Answer

B. it is useful for projects with repeated units like floors or roads

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

LOB helps plan repetitive work flow. Correct option: B.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account