For field interpretation of Earned Value, the issue is cost and schedule performance. What should be selected? Avoid the common trap that earned value uses only rainfall.
Construction ManagementEarned ValueMEDIUM
Choose the correct answer
A
schedule variance is always zero
B
actual cost is never recorded
C
earned value uses only rainfall
D
earned value compares planned value, earned value and actual cost
Correct Answer
D. earned value compares planned value, earned value and actual cost
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
EVM integrates scope, cost and schedule progress. Correct option: D.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.