Civil Engineering MCQJE Level Civil Engineering

For field interpretation of CPM, the issue is deterministic project scheduling. What should be selected? Avoid the common trap that critical path is always the shortest path.

Construction ManagementCPMEASY

Choose the correct answer

A

float is measured only in rupees

B

critical path is always the shortest path

C

CPM ignores activity durations

D

critical path has zero total float in the basic network

Correct Answer

D. critical path has zero total float in the basic network

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

CPM identifies activities controlling project duration. Correct option: D.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account