Civil Engineering MCQAE Level Civil Engineering

For an activity with ES=6, EF=14, LS=9, LF=17, early start of its sole successor=14, late finish of its sole predecessor=10, the independent float is:

Construction ManagementFloat TypesMEDIUM

Choose the correct answer

A

3 days

B

0 days

C

1 day

D

4 days

Correct Answer

B. 0 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

IF = max(0, ES_successor − LF_predecessor − Duration) = max(0, 14 − 10 − 8) = max(0, −4) = 0 days. Duration = EF − ES = 14 − 6 = 8 days. Independent float is often zero, meaning using total or free float does affect other activities. TF = LS − ES = 9 − 6 = 3 days.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account