Civil Engineering MCQAE Level Civil Engineering

For an activity with Early Start = 4, Early Finish = 10, Late Start = 7, Late Finish = 13, the total float and activity duration are respectively:

Construction ManagementFloat CalculationMEDIUM

Choose the correct answer

A

3 days and 6 days

B

6 days and 3 days

C

3 days and 7 days

D

4 days and 9 days

Correct Answer

A. 3 days and 6 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Duration = EF − ES = 10 − 4 = 6 days. Total Float = LS − ES = 7 − 4 = 3 days (cross-check: LF − EF = 13 − 10 = 3 days ✓). The activity can be delayed up to 3 days from its early start without delaying the project.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account