Civil Engineering MCQAE Level Civil Engineering

For a PERT activity with optimistic=3 days, most likely=7 days and pessimistic=10 days, expected time is

Construction ManagementOriginal practiceMEDIUM

Choose the correct answer

A

6.67 days

B

6.5 days

C

6.83 days

D

13.67 days

Correct Answer

C. 6.83 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

PERT expected duration: te = (a + 4m + b) / 6, where a = optimistic, m = most likely, b = pessimistic estimate (beta distribution approximation). Standard deviation sigma = (b - a) / 6; variance sigma^2. PERT is used when activity durations are uncertain; CPM uses single deterministic time estimates. Project duration variance = sum of variances on critical path. te=(a+4m+b)/6=(3+4×7+10)/6=6.83 days.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account