For a PERT activity with optimistic=3 days, most likely=7 days and pessimistic=10 days, expected time is
Choose the correct answer
6.67 days
6.5 days
6.83 days
13.67 days
Correct Answer
C. 6.83 days
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
PERT expected duration: te = (a + 4m + b) / 6, where a = optimistic, m = most likely, b = pessimistic estimate (beta distribution approximation). Standard deviation sigma = (b - a) / 6; variance sigma^2. PERT is used when activity durations are uncertain; CPM uses single deterministic time estimates. Project duration variance = sum of variances on critical path. te=(a+4m+b)/6=(3+4×7+10)/6=6.83 days.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.