For a bolted connection, pitch is 75 mm and end distance is 30 mm. The pitch refers to
Steel StructuresOriginal practiceMEDIUM
Choose the correct answer
A
Centre-to-centre distance of adjacent bolts along load direction
B
Distance from bolt centre to plate edge
C
Distance between gauge lines
D
Diameter of bolt hole
Correct Answer
A. Centre-to-centre distance of adjacent bolts along load direction
Why is this the answer?
Pitch is the longitudinal centre-to-centre spacing of bolts.
Related Steel Structures MCQs
More solved Steel Structures questions for AE/JE Civil Engineering exams.
- The 'residual stresses' in hot-rolled steel sections arise from:
- The 'effective slenderness ratio' for a single angle compression member (IS 800)...
- 'Fatigue failure' in steel structures occurs under:
- The 'tension field action' in a plate girder web after buckling means:
- Bolts in 'slip-critical' (HSFG) connections resist load by:
- The 'portal frame analysis' approximation for multi-storey frames under horizontal load...
Practice more Civil Engineering questions
This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.