Civil Engineering MCQJE Level Civil Engineering
During an JE solution review on Total Float, what is the safest statement about allowable delay of an activity? Avoid the common trap that it is independent of network logic.
Construction ManagementTotal FloatMEDIUM
Choose the correct answer
A
it is always negative
B
it is the time an activity can be delayed without delaying project completion
C
it equals direct cost
D
it is independent of network logic
Correct Answer
B. it is the time an activity can be delayed without delaying project completion
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Total float measures scheduling flexibility. Correct option: B.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.