Civil Engineering MCQJE Level Civil Engineering
During an JE solution review on Resource Levelling, what is the safest statement about adjusting schedule to smooth resource demand? Avoid the common trap that resource demand is ignored.
Construction ManagementResource LevellingMEDIUM
Choose the correct answer
A
levelling means changing concrete level only
B
non-critical activities may be shifted within float
C
resource demand is ignored
D
critical activities are always deleted
Correct Answer
B. non-critical activities may be shifted within float
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Resource levelling balances resource usage against schedule. Correct option: B.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.