During an JE solution review on PERT, what is the safest statement about probabilistic activity duration? Avoid the common trap that pERT is a soil test.
Construction ManagementPERTMEDIUM
Choose the correct answer
A
PERT is a soil test
B
PERT uses only one fixed duration
C
pessimistic time is ignored
D
expected time is commonly based on optimistic, most likely and pessimistic estimates
Correct Answer
D. expected time is commonly based on optimistic, most likely and pessimistic estimates
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
PERT handles uncertainty in activity durations. Correct option: D.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.