During an JE solution review on CPM, what is the safest statement about deterministic project scheduling? Avoid the common trap that critical path is always the shortest path.

Construction ManagementCPMEASY

Choose the correct answer

A

critical path is always the shortest path

B

CPM ignores activity durations

C

critical path has zero total float in the basic network

D

float is measured only in rupees

Correct Answer

C. critical path has zero total float in the basic network

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

CPM identifies activities controlling project duration. Correct option: C.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account