Critical path in PERT network is the one for which
Construction ManagementConstruction ManagementMEDIUM
Choose the correct answer
A
Most likely time estimate is the largest
B
Optimistic time estimate is the largest
C
Expected time estimate of the activities is the largest
D
Pessimistic time estimate of the activities is the largest
Correct Answer
D. Pessimistic time estimate of the activities is the largest
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
The critical path is the path having maximum expected duration
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to WBPSC AE Previous Years Questions Series. Full tests include timed attempts, rank comparison and subject-wise analysis.